Skip to main content

How To Use Production With Material Issue And Receipt

Use production orders to connect the required material, shop-floor activity, and output. GI Agst. Prod. Order issues material; GR Agst. Prod. Order receives production output. Both should refer to the intended order and, where required, the intended process.

Prepare Production Setup​

Confirm the finished item, component items, UOMs, plants, stores, and batch/serial requirements. Complete the appropriate BOM or Advance BOM, including materials, processes, and overhead used by the operation.

Review Production Order Types before entry:

  • GI Prod. Type, Plant, and Store identify the issue-side defaults.
  • Don't Allow GR Without GI and shortage/excess controls govern whether output can be received.
  • Process Based GI/GR Required, process dependency, and Process Confirmation Required govern the sequence of process activity.
  • Back Flushing Allowed supports automatic consumption based on output where configured.
  • Batch creation and closure settings affect traceability and pending quantities.

Agree whether the operation uses explicit goods issue or configured backflushing. Do not manually duplicate material consumption already created by the selected process.

Create The Production Order​

  1. Create a Production Order, or use Advance Production Order when the process requires it.
  2. Select the applicable order type and product/BOM, quantity, dates, and operational scope.
  3. Review material requirements, processes, overhead, and any sales-order or planning reference.
  4. Save and complete the required approval or release steps before attempting issue.

Issue Material Against The Order​

  1. Open GI Agst. Prod. Order, select New, and select a pending order.
  2. Enter issue quantity, plant, store, and process where required.
  3. Review loaded material lines, current stock, pending quantity, and issue quantity.
  4. Complete each line's store, rate, required cost centre, and batch/serial details.
  5. Keep issue within the permitted quantity and reconcile batch/serial totals to the line quantity.
  6. Save and review the issue document.

The issue date must be within the working financial year and not earlier than the production order. See Creating GI Agst. Prod. Order.

Confirm Processes And Receive Output​

Complete Process Confirmation when required by the order type.

  1. Open GR Agst. Prod. Order, select New, and select the pending order.
  2. Enter receipt quantity and the applicable process. Use Fetch Issue Rate where the receipt value should use issued material or process cost.
  3. Resolve pending process confirmations or GI shortages required by the production policy.
  4. Review output item, store, quantity, rate, batch/serial details, and required attributes.
  5. Review Consumption And Cost, including WIP consumption, processes, and overhead where enabled.
  6. Save and review the receipt.

The receipt date cannot precede the production order or related goods issue. Actual WIP consumption cannot exceed available WIP stock. See Creating GR Agst. Prod. Order.

Reconcile And Complete The Order​

Compare ordered output, issued material, returned material, received output, remaining quantities, and any WIP. Check process/overhead cost and receipt value before period-end valuation. Use Goods Return Agst. Prod. Order for the supported return flow instead of an unrelated stock adjustment.

ProblemWhat To Check
Order is missing from GI or GROrder status, pending quantity, selected plant/process, and permissions.
GR is blockedRequired GI, shortage controls, process confirmation, and date sequence.
Excess quantity is rejectedRemaining order quantity and the order type's excess controls.
Receipt cost differsIssued material, Fetch Issue Rate, WIP consumption, process costs, and overhead.
Order stays openRemaining quantities and configured automatic-closure rules.