Skip to main content

Importing and Exporting Standard Costs

The Import/Export tab is used when item standard cost values need to be maintained in bulk through Excel.

Before you begin​

Confirm that:

  • The item records already exist in ZipERP.
  • The user has permission to export and import item standard cost values.
  • The item group is known if the update is limited to a specific group.
  • The uploaded file is prepared from the exported format.

Exporting the current standard cost list​

  1. Open ERP > Inventory > Item Standard Cost.
  2. Stay on the Import/Export tab.
  3. Select Item Group if only one group should be exported.
  4. Leave Item Group blank to export all available items.
  5. Click Click Here beside the export instruction.
  6. Save the generated Excel file and use it as the working template.

The export includes the item details needed for review and the current Standard Cost value. Using the export as the update template helps keep the upload format valid.

Preparing the upload file​

Before uploading:

  • Keep the exported column structure unchanged.
  • Do not rename or remove the Code or Standard Cost columns.
  • Update only the standard cost values that need correction.
  • Keep item codes exactly as exported.
  • Enter standard cost as a numeric value.
  • Remove accidental blank rows from the working area.

Uploading standard costs​

  1. Open the Import/Export tab.
  2. Under Import Item Standard Cost List, choose the prepared Excel file.
  3. Click Upload.
  4. Review the success or error message shown after upload.

When the upload is accepted, ZipERP updates the standard cost for each valid item code in the file. If the file is not an Excel file, has no data, or does not match the exported layout, the upload is rejected and the costs are not updated from that file.

Good practices​

  • Export immediately before preparing a bulk update so the item list is current.
  • Keep a copy of the exported file before changing values.
  • Upload a smaller item group first when validating a new costing revision process.
  • Review high-value items after upload through the manual entry tab or the item record.