Creating an Advance BOM

Creating an Advance BOM starts with base manufacturing details. After the first page is completed, ZipERP opens the process and material mapping page.

Required first-page fields​

  • BOM Type: Required. Select the Advance BOM type.
  • Item: Required. Select the manufactured item.
  • Base Qty: Required. Enter the base quantity for which the process and material structure is defined.
  • Base UOM: Required. Select the base unit.
  • BOM Variant: Required. The variant identifies this version of the Advance BOM for the selected item.
  • Plant: Required. Select the plant where the Advance BOM applies.
  • Cost Center: Required when cost center tracking is active.

The item and BOM variant combination must be unique. ZipERP blocks saving when the same variant already exists for the same item.

Detail-page header​

On the detail page, review the carried header values, enter remarks, add attachments if needed, and decide whether to Send for Approval.

Save​

Add at least the required process structure and related material details, then select Save. If approval is selected, the Advance BOM is submitted to the configured approver.