Process and Material Mapping

The Process & Material Mapping tab is the core of Advance BOM. It defines the manufacturing process tree and the items linked to each process.

Process lines​

Each process line can include:

  • Process code and process name
  • Department
  • Internal or external process type
  • User or vendor, required for external process handling
  • Machine
  • Required time
  • Cost
  • Sub-process level

Process code and process name are required. When a process is external, the vendor must also be selected.

Adding materials to a process​

Use the process line action to add item details under that process. Each item line includes:

  • Item code and item name
  • Quantity
  • UOM
  • Item type
  • Issue or receive type
  • Cost center, when required
  • Description and attributes, when applicable

Item, quantity, UOM, item type, and issue/receive type are required. Use issue/receive type carefully because it controls whether the item is consumed by the process or received from the process.

Sub-processes​

Use sub-process actions to build a hierarchy under a process. Sub-processes help represent multi-step production where each step has its own materials, time, machine, vendor, and overheads.

Sub BOM​

When a selected item has an Advance BOM variant of its own, ZipERP can bring sub-BOM process and material details into the structure. Review the imported process tree before saving.