Editing Purchase Requisitions

Editing is used to correct requisitions that have not moved too far in the purchase process.

When Editing Is Allowed​

Users can edit a requisition only when:

  • They have edit permission.
  • The document is not locked by another user.
  • The document is not approved, rejected, or pending approval in a way that blocks editing.
  • No purchase order has been posted against the requisition.

When Editing Is Blocked​

The system blocks editing or deletion when:

  • A purchase order has already been posted against the requisition.
  • The document is approved.
  • The document is rejected.
  • The document is waiting in an unapproved approval state.
  • Another user is currently working on the document.

These restrictions protect purchase history and prevent changes after the buying process has already started.

What Can Be Corrected​

When editing is available, users can correct the same business areas used during creation:

  • Header details such as department, buyer group, plant, cost center, and delivery date
  • Item or service lines
  • Quantities and UOM
  • Descriptions and remarks
  • Attachments
  • Approval submission choice

When the requisition came from a reference document, the quantity still cannot be increased beyond the pending reference quantity.

Good Practice​

  • Do not change the department or plant casually after a requisition has been reviewed.
  • Add a remark when the correction changes buying expectations.
  • Confirm that approvers and buyers understand why the requisition was changed.
  • If purchase order activity has already started, create the required correction in the downstream purchase document instead of trying to alter the requisition.
Mobile App Availability

This functionality is not available on the mobile app.